MAXIMIZING THE PROFIT OF A HPP CASCADE CONSIDERING HYDRAULIC LINK VIA RESERVOIRS

Journal Tekhnichna elektrodynamika
Publisher Institute of Electrodynamics National Academy of Science of Ukraine
ISSN 1607-7970 (print), 2218-1903 (online)
Issue № 5, 2016 (September/Oktober)
Pages 70 – 72

 

Authors
A.Y. Mahnitko1, J.H. Gerhards1, T.V. Lomane1, R.V. Varfolomejeva1, V.P. Oboskalov2, K.S. Koljasnikov2
1 – Institute of Power Engineering, Riga Technical University,
Azenes str., 12/1, Riga, LV-1048, Latvia
2 – Ural Federal University,
Mira str.,19, Yekaterinburg, 620002, Russia,
e-mail: Этот e-mail адрес защищен от спам-ботов, для его просмотра у Вас должен быть включен Javascript

 

Abstract

At the conditions of market relationships and economic and financial independence of power companies, these are guided by the principle of achieving maximum efficiency in their actions. In the article is considered the problem formulation of HPP cascade operational mode determination, ensuring maximum profit from the sales of the generated electric power at the day-ahead market. Dynamic volumes of reservoirs are taken into account using the lag time between the waves of HPP water flow. The problem solution using the method of statistical modelling is approbated on the example of hypothetical cascade of three HPP. The results of the modelling of cascade operating regime are illustrated graphically. References 5, figures 2, table 1.

 

Key words: HPP cascade, regime, capacity, head level, time flow lag of water.

 

Received:    03.02.2016
Accepted:    23.05.2016
Published:  13.09.2016

 

References

1. Gornstein V.M. Optimal Operation Hydro Power Plants in Power Systems.  Moskva: Gosenergoizdat, 1959.  248 p. (Rus)
2. Reznikovskii A.S., Rubinstein M.I. Modes Control of Hydroelectric Power Plants Reservoirs. Мoskva: Energiia,1974. 176 p. (Rus)
3. Tsvetkov E.V., Alyabysheva T.M., Parfenov L.G. Optimal Regimes of Hydropower Plants in Power Systems.  Мoskva: Energoatomizdat, 1984.  304 p. (Rus)
4. Radu Popa, Florica Popa, Bogdan Popa, Manuela Nicolescu. Optimal Operation of Cascade Hydropower Plants. U.P.B. Sci.Bull. Series D.  2010.  Vol. 72.  Iss. 1.  P. 93–100.
5. Mahnitko A., Gerhards J., Linkevics O., Varfolomejeva R., Umbrasko I. Small Hydropower in Latvia and Intellectualization of its Operating Systems. Latvian Journal of Physics and Technical Sciences.  2013.  Vol. 50 (6).  P. 3–15.

 

PDF